WNCRRd
April 1st 1878
Gentlemen
I have the honor to submit the following estimate of work done for the quarter ending March 31st 1878.
22600 Yds of Earth @ 20 c $4520
14300 Yds of Rock @ 1.00 14300
900 Yds of Tunnel @ 4.00 3600
Total $22420
Respectfully submitted
Jas. W. Wilson
Presdt
To the Board of Directors
Western NCRRd